A CMMS in Excel is a workbook that keeps assets, maintenance plans, work orders and history as lists and works out due dates. For one site with a manageable set of assets, you can start with it today. This guide covers structure, data, limits and the path to software, as of October 2026.
Key facts at a glance:
- Structure: one sheet each for assets, maintenance plans, work orders and history, linked by fixed IDs
- Due dates: formulas work out the next date from the last execution and the interval
- Limits: no reminders, no macros in the mobile Excel apps, co-authoring only in OneDrive or SharePoint Online
- Template: free, in English and German, with an optional macro module
- Switching: flyze takes over the assets, maintenance plans and work orders of the template into flyze.platform
You get the template free of charge through the form at the end of this article: Go to the template.
What is a CMMS and how does it help with maintenance?
A CMMS (computerised maintenance management system) is software you use to plan and track maintenance work. In German-speaking plants, it is often simply called maintenance software.
DIN 31051 (2019-06 edition), the German standard on the fundamentals of maintenance, divides maintenance into four basic measures: servicing, inspection, repair and the improvement of functional reliability. According to EN 13306, maintenance covers all technical, administrative and managerial actions that keep or restore an item so that it can perform its required function. A CMMS helps in three ways:
- Planning: it works out due dates and shows what comes next.
- Control: every work order has a status, a priority and a person in charge.
- Records: the history shows, for each asset, who did what and when.
Why Excel is a good start for structured maintenance
Excel is a good start because your team already knows spreadsheets and the first list needs no IT project. Every formula is visible, and every column can be changed. So you practise structure before you choose software.
Recording machines and assets in one place
A central asset list replaces scattered notes, folders and the private lists of individual colleagues. In Excel, one row per asset with ID, name, location and manufacturer is enough. Anyone looking for an asset filters the list instead of asking around. The flyze template has 16 columns, including serial number, year of construction and commissioning date. Even this list shows which assets are critical for operations.
Setting maintenance intervals and responsibilities
In Excel, you set the interval and the person in charge of each maintenance task in the same row. A formula works out the next date from the last execution and the interval. The plan then no longer lives in one colleague’s memory but in a file everyone can read. If an interval changes, you change one cell, and the date recalculates.
Documenting work orders and completed maintenance
In Excel, every work order becomes a row with number, asset, status and due date. Whoever completes it enters the date, the solution and their own name. Requests shouted across the hall and sticky notes become a list you can filter by asset, person or status. The completed rows form the history of each asset.
Getting an overview of open and overdue tasks
A start sheet that counts the lists with formulas gives you the overview. The flyze template shows ten key figures there as tiles. They include open and overdue work orders, maintenance due and open faults. Two charts show work orders by status and maintenance by due date. Because the formulas use today’s date, a date turns overdue without anyone doing anything.

How can you structure maintenance with Excel?
Structure maintenance in Excel with four linked lists: assets, maintenance plans, work orders and history. Each list gets its own sheet with one header row and one row per entry. The asset ID links the sheets, because plans and work orders carry it.
Creating an asset list as the basis for maintenance
Start with the asset list, because every plan and every work order refers to an asset. Give each row an ID with a prefix for its level, for example AST-101 for an asset. A column with the parent ID places each row, from site via area and asset down to component. Status and criticality, meaning how hard a failure hits operations, come from fixed lists.

Building maintenance plans with intervals and due dates
Create one row per maintenance task, not per asset, because an asset can have several tasks. Each row names the asset, the type of maintenance, the interval type (days, weeks, months or years), the interval and the last execution. From these, a formula works out the next due date, by the calendar for months and years. Two more columns show the days left and the status: OK, due soon (within 14 days) or overdue.

Managing work orders with status and responsibilities
Keep work orders in a list of their own with a running number, for example WO-2026-0001. Each work order names its type, asset, priority, person in charge and due date. The status comes from six values: Open, Scheduled, In Progress, Waiting for Parts, Completed or Cancelled. A traffic light marks what is overdue and what falls due within 3 days.

Documenting maintenance history and faults traceably
The history becomes traceable when every completed work order carries the date, the solution, the duration and the person who did the work. Record faults as a work order type in the same list, so they appear in the history of their asset. In Germany, you record the results of inspections of work equipment under section 14(7) of the Ordinance on Industrial Safety and Health (BetrSichV, in German). The record states at least the type, scope and result, plus the name and signature of the person qualified to inspect. You keep it at least until the next inspection, electronically if you wish; for installations requiring monitoring, section 17 applies. In the template, you link the signed inspection record on the documents sheet.
Which data belongs in a CMMS Excel template?
A CMMS Excel template needs asset master data, maintenance tasks with intervals, work orders with status and the work done. Order matters more than the number of columns: one ID per row, one header row per list and fixed value lists. This order makes the data transferable later.
Asset master data and unique asset IDs
An asset’s master data includes its name, type, manufacturer, model, serial number, year of construction and location. Status, criticality, the person responsible, operating hours and the commissioning date come on top. The ID matters more than any field: it occurs only once and never changes. A prefix per level, for example SITE for site and CMP for component, makes the ID readable.
Maintenance tasks, intervals and next due dates
A maintenance task needs at least the asset, type, description, interval and the date of the last execution. The template knows six types: inspection, service, test, calibration, cleaning and lubrication. You do not type in the next due date; a formula works it out. Duration, priority, responsibility and an active column complete the planning; an inactive plan gets no date.
Responsibilities, status and completed work
Every plan and every work order names a person in charge. Choose the status from a fixed list so that filters and key figures count correctly. The template’s drop-down lists suggest values but also accept typed ones. A status typed by hand is then missing from the work order chart. Completed work includes start, completion, actual duration, solution and the person who did it.
Faults, working hours and spare parts
A fault needs the asset, a description, a priority and the date it was reported. Working hours sit on the work order as actual duration in hours, material and labour as costs in euros. The template records spare parts only as costs, not as a store with stock and storage location. Anyone who wants to reserve or reorder parts needs a separate list or a system for it.
Where does Excel reach its limits in maintenance?
Excel reaches its limits as soon as several people work at the same time or technicians report back from the asset. In a spreadsheet, due dates do not trigger work orders. Records and key figures depend on the care of individuals.
When several people work on work orders at the same time
A workbook can only be co-authored in OneDrive or SharePoint Online, not on network drives or in local folders. If someone opens the file in an older version such as Excel 2016 or 2019, it is locked for everyone else. If two people change the same thing, the last saved change generally wins. Microsoft therefore advises giving each person their own areas or sheets. That advice fits a shared work order list poorly.
When maintenance dates must be monitored automatically
A workbook works out dates but sends no reminders: an overdue date only shows when someone opens the file. With the VBA module, the Complete Work Order button updates the last done date in the plan, and Create Work Order turns a plan into a work order. But someone has to click: a due plan does not create a work order by itself. Intervals run by the calendar only; operating hours trigger nothing. The lubrication plan case study shows what a lubrication plan by operating hours from the control system looks like.
When technicians should handle work orders right at the asset
At the asset, Excel fails in two places: macros do not run, and the spreadsheet does not fit a phone. The mobile Excel apps do not run VBA (Visual Basic for Applications) macros. They open workbooks with macros, but the template’s buttons do nothing. Macros do not run in Excel for the web either, and no message says so. The template’s work order list has more than 20 columns.
When a reliable asset history and meaningful KPIs are missing
History and key figures only become reliable when nobody changes entries unnoticed and every failure carries a start and an end. In Excel, anyone with write access can change completed work orders; Microsoft expressly says that sheet protection is not a security feature. In the template, the history is only a view: deleting a work order deletes it there too. MTTR (mean time to repair) measures the average time to restoration. MTBF (mean time between failures) measures the average operating time between failures. For both, the work order list lacks the times of failure and restoration.
When several production lines, sites and systems come together
With several lines, sites and systems, the problem is not the number of rows but the number of files. A worksheet holds 1,048,576 rows. It gets difficult when each line keeps its own file with its own IDs. In the template, assets, maintenance plans and work orders hold 400 rows each, and the history shows up to 400 completed work orders. Anything beyond that is missing from key figures and history. Someone enters operating hours from the controller and orders from the ERP (enterprise resource planning) system by hand.
Excel or CMMS software: when is it worth switching?
Switching pays off as soon as one of the five limits shapes your daily work. Until then, Excel is enough, and every well-kept list makes the later move easier. The table compares both sides:
| Criterion | Excel is enough | A CMMS pays off |
|---|---|---|
| Editing | One person keeps the file | Several people edit at the same time |
| Dates | Intervals by the calendar | Also by operating hours and plant calendar |
| Work on site | Feedback in the office | Recording on the phone at the asset |
| Records | List of completed work orders | History of every change with person |
| Scope | One site, one file | Several lines and sites |
| Systems | No connection needed | Data from controller and ERP |
Excel for getting started and manageable maintenance tasks
Excel is enough as long as one person keeps the plan, intervals run by the calendar and feedback arrives in the office. At the start, the spreadsheet even has an advantage. It shows which data you really keep and which columns stay empty. You take this knowledge into any later selection.
A CMMS for automated planning and mobile work orders
A CMMS pays off when dates should trigger work orders by themselves and technicians should report back from the asset. It creates the work order from a due plan and works out the next date after completion. Technicians see their work orders on a phone or tablet and record readings and photos on site. Every change carries a person and a time, without anyone adding them later.
Which functions your maintenance really needs
You can read the functions you need from your current list: every column you keep is a requirement. Five functions form the core:
- Asset structure with unique IDs
- Maintenance plan with intervals and due dates
- Work orders with status and responsibility
- Recording at the asset, even without a network
- History with a record of every change
Spare parts, key figures and connections follow once this core holds up in daily work.
Why your own processes matter more than a long feature list
Your processes matter more because a function only helps if it fits your workflow. A long list says nothing about whether your approvals, inspection steps and terms fit into it. If the software does not fit, special cases move into comment fields and side lists, and the spreadsheet returns. So test with real work orders, not with features on paper.
From Excel to your own CMMS: how to take the next step
The next step works in four stages: start small, write down processes, test with real work orders and take over the data. Each stage uses what your Excel list already contains. So the new system does not start from zero.
Starting with a manageable set of assets
Start with one area, such as a line or a process stage, rather than the whole plant. Choose assets with high criticality and tasks that slip past their deadline today. A limited scope shows early whether structure, terms and processes hold up. More areas and sites follow once the first one works in daily operation.
Documenting existing processes and requirements
Write down how a work order runs today: who reports, who decides, who carries it out and who closes it. In your Excel list, mark columns that nobody maintains and details that only sit in remarks. This gives you a short list of requirements, split into must-haves and nice-to-haves. Also note which systems supply data, such as the controller or the ERP.
Testing the key functions with real work orders
Test with work orders from last month, not with the vendor’s examples. Take a fault, a maintenance task and an inspection with a photo. Play each one through from report to completion. Let technicians record the data themselves, at the real asset and on their own device. Note where a step gets stuck and which detail is missing.
Taking over Excel data and digitising step by step
Take over your Excel data instead of retyping it, and prepare the list for it. Every row needs a unique ID, every sheet exactly one header row. Store dates as dates, not as text, and unmerge merged cells. Take over assets first, then maintenance plans and open work orders, and the history last. After that, digitise further processes step by step, such as inspections with a checklist.
Frequently asked questions about CMMS and Excel
Can Excel be used as a CMMS?
Yes, as a start Excel can serve as a simple CMMS. Assets, maintenance plans, work orders and history can be kept as linked sheets, and formulas work out the due dates. Reminders are missing, and macros do not run in the mobile Excel apps. For one site where one person keeps the file, that is enough.
Is there a free CMMS Excel template?
Yes, flyze offers a free CMMS template for Excel, in English and German. It has sheets for assets, maintenance plans, work orders, history, documents, photos and users, plus a start sheet with key figures. An optional VBA module for desktop Excel adds buttons, work order numbers and a sign-in with a PIN. Roles and PINs organise the work; the PINs are readable in the file. You get the template through the form at the end of this article, in return for your name and email address.
Which functions should maintenance software offer?
Maintenance software should offer an asset structure, a maintenance plan, work orders, mobile recording and a history with a change log. Besides the calendar, the maintenance plan should know counters such as operating hours. On site, photos, readings, a signature and working without a network count. Interfaces to the ERP and the controller save entering data by hand.
When is Excel no longer enough for maintenance?
Excel is no longer enough once several people work on work orders at the same time or technicians should report back from the asset. Other signs are dates by operating hours, records with a change log and several sites with their own files. If someone asks for key figures such as MTTR, the spreadsheet lacks the times of failure and restoration.
Can you take data from Excel into a CMMS later?
Yes, if the list is in order. That means one ID per row, one header row per list, fixed value lists and dates stored as dates. Then every row can become a record without retyping. Free text, merged cells and details in comments cost rework in any takeover. The last chapter shows how flyze takes over your list.
How does flyze.solutions help you move on from Excel?
When Excel is no longer enough, moving to flyze.platform is easy. We take over your list. The asset structure of flyze.platform has the same four levels as the template: site, area, asset and component. With fixed IDs, one header row per list and fixed value lists, flyze takes over assets, maintenance plans and work orders without anyone retyping them. This is how flyze supports the steps that follow:
- Maintenance plan: The maintenance plan of the maintenance software derives every next date from the last execution. It checks the date against the maximum interval of the requirement and shows conflicts with shutdowns and public holidays months in advance.
- Work orders: The Work orders app shows every work order as a card on a board, with person, date and priority. The board also shows what is overdue.
- At the asset: The Field service app guides technicians through every step on a phone or tablet, even without a network. On completion, readings, photos and findings become the record.
- Records: In the Asset Explorer you view and maintain the asset data. Its journal records who changed which field and when, with the old and the new value.
- Operating hours: Through flyze.edge, operating hours and other values from the controller can trigger maintenance and inspections automatically.
- Key figures: In the building kit you build a dashboard from widgets, for example for open and completed work orders.
The case study from a refinery shows how an inspection moved from Excel, email and paper to the tablet.
SCADA (supervisory control and data acquisition), MES (manufacturing execution system) and ERP stay in operation; flyze connects to them.
A pilot project with one area and the plans from your template shows results within weeks. Find your entry point shows which start fits. To arrange a conversation, write to us through the contact form.
The CMMS template for Excel
The template is free. After you submit the form, the next page takes you to the ZIP file with the workbook, the VBA module and the manual.