Skip to content

Ask AI

What happens when our requirements go beyond off-the-shelf software?

Book a demo
Plant Connectivity & Data

500 sites. One dataset for the EKVO report.

A wastewater association keeps the master data of its 500 or so sites in the Asset Explorer. flyze.edge reads it for the EKVO report.

  • Case study
  • Energy & utilities
  • Published
Photo: a wastewater treatment plant from the air, round tanks with domes and rectangular basins, buildings and paths between them, fields and woodland in the haze behind.

Wastewater association Anonymised customer reference

Sector
Wastewater
Application
Master data for the EKVO report
Integration
flyze.edge to ACRON
Scope
About 500 sites
Portrait of Manuel Stotz

In short

“A wastewater association now keeps the master data of its 500 or so sites in one place. To do this, we organised its sites in the flyze.platform’s Enterprise Asset Management, from association to structure. flyze.edge reads the current data from there for its reporting system. The yearly reconciliation before the report under the self-monitoring ordinance, the EKVO, is gone.”

Manuel Stotz Founder & Managing Director, flyze.solutions GmbH

01 The company

An association with about 500 sites

Our customer is a wastewater association. It runs about 500 sites: treatment plants, pumping stations, stormwater tanks and other special structures in the sewer network. For each of them, it keeps master data: the fixed details on location, equipment and operation.

Once a year, the association reports under the EKVO. This German self-monitoring ordinance sets out how operators monitor their own wastewater facilities and report on them. The association produces the report in ACRON, a software for operating data and reports.

  • About 500 sites Treatment plants, pumping stations, stormwater tanks and special structures in the sewer network.
  • One report a year The EKVO report lists the active treatment plants and pumping stations.
  • Reports from ACRON The software collects operating data and produces the report.

02 The challenge

The yearly reconciliation before the report

The master data sat in spreadsheets that each department kept for itself. Before every EKVO report, someone compared these spreadsheets with the plant list in ACRON. The check covered new, changed and decommissioned plants.

Each site also has data that the report doesn’t need but operations do:

  • Water rights: permit, notice and deadline
  • Energy: supplier, meter and annual consumption
  • Responsibility: plant manager and contact
  • Structure: drive, throttle, material and year built

The reconciliation in four steps

Before every report, the same process repeated:

  1. Collect spreadsheets Each department sends its current version.
  2. Compare Someone checks row by row against the list in ACRON.
  3. Ask back Each difference goes back to the department in charge as a question.
  4. Correct The corrections go into the report list by hand.

Next year, the reconciliation starts again.

An example: the decommissioned pumping station

A pumping station goes out of service because, after a rebuild, the wastewater flows by gravity. The operations department records this in its spreadsheet. In the report list, the pumping station stays.

Only the reconciliation before the next report shows the difference. Until then, there are two spreadsheets with two versions. Only whoever asked last knows which one applies.

The effects day to day

  • The same detail sat in more than one spreadsheet, not always with the same value.
  • Every year, the reconciliation took experts’ time shortly before the report was due.
  • Anyone looking for a past change found neither the person nor the date.

03 The approach

Data model first, then the integration

First, we agreed with the departments which data belongs to which site. This produced one asset type per type of structure, for example treatment plant, pumping station or stormwater tank. The type sets the fields, with unit, required entry and selection list.

Then we set up the sites in the flyze.platform’s Enterprise Asset Management (EAM) and took over the existing spreadsheets. Since then, each site appears exactly once in the asset tree, maintained in the Asset Explorer. Finally, we connected ACRON through flyze.edge, the interface between the flyze.platform and other systems.

What the association decided

The association set three rules itself:

  • One type per type of structure

    A treatment plant has different fields from a pumping station. So each type of structure gets its own asset type.

  • Selection lists instead of free text

    Process, drive or throttle type come from fixed lists. So every department enters the same value the same way.

  • Decommissioned means: not in the report

    A decommissioned site stays in the Asset Explorer. The EKVO report only lists plants in operation.

Each department knew its own spreadsheet best. Together, we turned them into one data model for the whole association. The EKVO report benefits first, and the work at the plants comes next.

Manuel Stotz Founder & Managing Director, flyze.solutions GmbH

The data model

From structure to report How the parts fit together:

  1. Asset: each site, once in the asset tree
  2. Asset type: the fields per type of structure
  3. Aspects: groups such as operation, water rights or energy
  4. Selection lists: fixed values instead of free text
  5. Status: in operation or decommissioned
  6. flyze.edge: reads the current data for the report
  7. ACRON: produces the EKVO report

04 The benefits

One dataset for operations and reporting

The Asset Explorer shows the answers to three questions that were open before every report:

  • Which plants belong in the report?

    For the report, flyze.edge reads all treatment plants and pumping stations in operation. Whoever decommissions a plant changes its status, not a second list.

    More on flyze.edge
  • Where is the current detail?

    Each site has exactly one record in the asset tree. Permit, energy supplier and responsibility sit in the same place as the equipment data.

    More on asset management
  • Which fields does a type of structure need?

    The association sets fields, units and selection lists per asset type. A new detail becomes a new field in the type, and every site of that kind has it.

    More on the building kit

05 The result

An asset register for every site

The Asset Explorer shows each site with its master data, its status and its history. On the left is the asset tree, from the association down to each structure. The master data sits next to it, and on the right are notes and the journal with every change.

From structure to report

  1. Change A pumping station gets a new pump or goes out of service.
  2. Enter The department changes the master data in the form.
  3. Trace The journal stores person, time and old value.
  4. Report For the EKVO report, flyze.edge reads the current data.

Nobody reconciles spreadsheets before the report. Anyone looking for a detail finds it in one place.

The asset tree: association, area, group and plant, each site exactly once.All screenshots show the click demo with sample data. You’ll find the demo at the end of the page.

All sites in one structure

Before Each department kept its own spreadsheet, with its own layout.

With flyze One asset tree orders all sites by area and group.

The directory shows every level as a table, with one tab per type of structure. Filter and search find a plant by name, number or type.

Directory: one tab per type of structure, each plant with path, status and master data.

Master data per type of structure

Before Columns each department filled differently, and values as free text.

With flyze The asset type sets every field, with unit, required entry and selection list.

Aspects such as operation, power supply and location structure the master data. The department changes it in the form, which checks required fields and units.

Master data: grouped by aspect, every value with its unit.

In operation or decommissioned

Before A decommissioned plant stayed in the report list until someone deleted it.

With flyze The status is part of the master data, and flyze.edge only reads plants in operation.

The decommissioned site stays in the Asset Explorer with its history. A note says why it went out of service.

Decommissioned: the plant stays in the register with status and note, but without appointments.

Every change in the journal

Before No spreadsheet showed who had changed a detail.

With flyze The journal stores every change with person, time, old and new value.

The takeover of the old spreadsheets is in the journal too. So anyone can trace every value back to its source.

Journal: every change with date, person and message.

06 The integration

Master data to ACRON via flyze.edge

flyze.edge connects the flyze.platform to other systems. When the association produces the EKVO report in ACRON, flyze.edge reads the master data from the EAM. From it, ACRON receives the list of treatment plants and pumping stations in operation.

The association set the rule for this itself, and it applies to every report. When a department changes a site, the change is in the next report without any further step.

  • flyze.edge reads the master data. Only authorised people change it, in the Asset Explorer.
  • Decommissioned sites stay in the Asset Explorer, and the report doesn’t list them.
  • The association exports all master data at any time as CSV or PDF.

07 The outlook

Inspections and work orders at every site

The master data is the basis for the next step: workflows at the sites. A workflow guides through a task step by step and stores the result at the plant. The association plans three kinds:

  • Visual inspections

    Rounds at pumping stations and tanks, with findings and photos recorded at the plant.

  • Maintenance and repair

    A finding becomes a work order, with date, person and feedback.

  • Recurring inspections

    Electrical tests or manhole checks with a fixed interval and a date in the calendar.

The click demo already shows this step with sample data.

Workflows at the pumping station: three tasks with interval and next appointment.

08 The conclusion

Kept once, current in the report.

The association keeps the master data of its sites in one place. For the EKVO report, flyze.edge reads the current data, and the manual reconciliation is gone. The rule for decommissioned plants applies to every report.

Your benefits at a glance:

  • all sites in one asset tree, from the association down to each plant
  • master data with fixed fields, units and selection lists per type of structure
  • the EKVO report with current data, without manual reconciliation
  • decommissioned plants in the register, but not in the report
  • every change in the journal, with person and time

The data was there, but spread across spreadsheets. Now the association keeps it in one place. And for every report, flyze.edge reads the version that currently applies.

Manuel Stotz Founder & Managing Director, flyze.solutions GmbH

The click demo to try

The demo shows the Asset Explorer with sample data from a fictional water association. You can click every view.

A click demo with your plants

Bring your plant list. We’ll load it into a click demo and show you the Asset Explorer with your data before you decide.

Request a conversation

Ready for the next step?

Requirements become digital solutions.

From the first conversation to live operation: we build solutions that fit your processes ... with flyze.platform, custom digitalisation and AI.

Subscribe to our newsletter

Always up to date. Inspiring content, trends & news

Almost done: please confirm your sign-up with the button in our email.

That did not work. Please check your business email address and try again.

Thank you, your sign-up is confirmed.